PANELS
1.DRYSTORAGE

1.Before delivery, we will give you the drawing (splicing pic. Of the position+construction pic.) of your customized size , technique parameters, and we will also label numbers of wall, floor, roof, door, and installment position and sequence.
2.According to the position labeled on the drawing, you should find the panel labeled on the same place and splice them in accordance with sequence. Every panel have groove or Convex slot(also called Male female slot), Eccentric hook, look at the pic:
As the Eccentric hook pic (refer above red arrow),connect the groove with Convex slot(Aluminium Tees in red), tighten the Eccentric hook by HEX SOCKET handle(Aluminium Tees), now the two panels are fixed, the other panels assemble by the same method. After the floor, walls, door, roof are installed, a whole cold room is ok now.
Look at the pics, the panels are now be put together
installation procedure: If below information not help you can ignore it .
The first step
The second step: install the panel corner, we should install the corner first, then the other walls.
The third step: after installing the corner, then add the wall one by one(according to our drawing)
These holes are the hook latch position, we should tight by tools. The Concave and convex chamfer between panel should install well (look at the details)
The forth step: install the door frame and the door (hinged door have this step, sliding door installation at the end)
Assemble the one by one, just like Fight puzzle, now the wall panel and the baseplate are ok.
The fifth step: install the ceiling
With the floor installed,we should install the sliding door
This is the installation instructions. After complete,we will give Specific instructions according to the actual situation.